Last August, UGKAP received a grant which paid for new shea transformation
equipment. This documents the
process of getting our shea complex machines wired to the electricity so we can
actually use them.
-68.000 (approx. $136) paid on August 30 to increase the
capacity of the counter
The hallway where you spend hours stalking the director's office, trying to find an opportunity to get inside |
-in November we paid 435.000 (around $870) for the larger
counter, the 4 new wires, etc.
They promised to come do the work at the latest in February, and showed us
the dimensions of the panel and panel cover that we need to have made, which we
did right away.
-At the beginning of March (the work is still not done),
they informed us that we overpaid and needed to come get our change—234.396
($368) was all we had needed to pay--what was this extra $500 for?! At the same time, we paid for a new panel b/c ours was the
wrong size.
-Mid-March they came to install the new wires. They then informed us that the cover we
bought for the counter box was too small (even though we bought the exact one
they told us to) and told us what size to make the new one. They left the wires and never returned
to do the work. We were also told to call an electrician to come and
disconnect the counter that is already in place and move it so that it can be
used for the office space and the complex counter can be separate. This work was all finished in less than
a week.
Attempting to meet with the head of branching. Check out the awesome wiring job he has done for his own lights... |
-Finally, only after I pulled the foreigner card and
showed up with our accountant in mid-April, we got someone to say they would
come and do the work. They do not
show up at the time they said they would so I proceeded to call every 30
minutes until they finally come, at COB.
-While doing the work we are informed that they are taking
the first counter back with them and the whole office will have to run off of
the same counter on a pre-pay system, even though we had earlier signed and
agreed to having 2 separated counters: one for the machine complex and one for
the office. They install the new
counter but tell us that we have to call an electrician to actually connect the
wires. I start losing my temper
with the dude so he finally agrees to just do it. However, when the work is finished the power for the
neighborhood has been cut so we can’t test to see if everything works.
-The next day: naturally, the power still doesn’t work. We have to call the electrician anyway
and get him to fix whatever they did wrong. One week later, we finally have functioning electricity in
the office and for the machines again.
It took almost 8 months, over $550, 10 sets of photocopies of the same receipts,
and at least 25 visits to the office to finalize what initially seemed like a simple task. And this, my friends, one of many reasons why change takes so unbearably long.
Main entrance to the office |